- It seems that the branch to Melaka will also be installed in the near future (if not immeadiately); in several reports, Moratel uses BDM term (Batam-Dumai-Melaka) instead of MBDC
- Length: 500 km (seems, incl. branch to Melaka)
- Investment: USD 40 mn
- GMSL is on the board! (Subcon from Triasmitra??)
- Installation target: Batam-Dumai (08/2009); Dumai-Melaka (09/2009)
- Inland segment: Dumai-Palembang-Lampung-Kalianda-Anyer-Jakarta (08/2009)
Showing posts with label MBDC. Show all posts
Showing posts with label MBDC. Show all posts
Sunday, July 26, 2009
Moratel - Updates
Just found something related to Moratel and its new cable MBDC, that might be of our interest :-D
Thursday, May 21, 2009
Moratelindo Batam Dumai Cable (MBDC) System
Now it is official! Moratel has silently revealed that they currently prepare Batam Dumai undersea cable system. The project is named "Moratelindo Batam - Dumai Cable" (MBDC). It shall extend their international connection via MIC-1 system to Sumatra mainland and from there to other domestic locations.
Moratelindo Batam Dumai Cable :
Moratelindo Batam Dumai Cable :
- Capacity: 12 FP; @ 8 Lambda
- Length: 380 km
- Landing points: Batam, Dumai
- Branching to Melaka/Malaysia prepared
- Contractors : NSW (cable vendor), PT. Ketrosden Triasmitra (main contractor)
- Construction : 10 months; RFS target August/2009