Without new arrangements, the consortium would have only USD 120 mn left for the entire project. It could mean that the overall system shall be shorter and some landing candidates are removed from the list. To my guess, at this budget figure, the total system length would be around 1,500 - 2,000 km in total (or less at current price) with around 10 landing points (or less, depending on what kind of landing facilities to be installed). And I'm afraid, it wouldn't sufficient for a ring! Such a distance is comparable to the distance of Jakarta, Singapore and going back to Jakarta. Already guessed my point ? .. Yupe, without additional budget, Palapa Ring would be better to be changed to "Palapa Bus" or "Palapa Fishbone" :-D. What do you think? :-D