Friday, January 16, 2009

JaKa2LaDeMa

I've just followed a news entry fed to my reader from Subtel. It's about Jaka2ladema, I've mentioned here several months ago. Well, it's for me quite a bit surprise that Telkom announced officially its project. Or could it be just the suppliers' initiative ? :-D . In any case, my congrats to Fujitsu/NSW! I do hope that NEC does the similar thing, since BSCS is not a secret project, right ? :-D
  • Suppliers/Contractors : Fujitsu-Norddeutsche Seekabelwerke (NSW)
  • CAPEX: more than USD 100 mn
  • Connects Kalimantan-Sulawesi; Java, Bali, Lombok
  • RFS schedule : Q1/2010
  • Hybrid repeatered/repeaterless system + BUs
  • Cables: LW, LW protected, SA, DA -- NSW's MINISUB
Source/Courtesy : Telkom/Fujitsu-NSW/Subtel

*Update - Kompas|Bisnis|Detik|Telegeography*

  • CAPEX : USD 115.41 mn | IDR 1.26+ tn
  • Capacity : 320 Gbps (which segment?)
  • Length : 1,836 km (total); (Ring 4 i.e. Pontianak-Ketapang-Pangkalan Bun-Banjarmasin --> 1,198 km; Ring 8 i.e. Sangata-Donggala--> 326.4 km; DMCS i.e. Benduluk-Denpasar-Mataram --> 312 km ??? -- need more explanation; press typo ??)
  • Contract signed : 30 December 2008
  • Primetrica : "Under the deal, Fujitsu is providing terminal equipment, repeaters, branching units’ system integration and related services for the JaKa2LaDeMa project. NSW is providing surveying, marine installation and civil works, and will also integrate Fujitsu’s repeaters into the repeatered cables it is deploying."